NYSE-listed Gulfmark Offshore has delayed the delivery of a newbuilding under construction at Norway's Simek shipyard by 11 months.
The vessel, which is being constructed for use in the North Sea, will now hit the water in January 2017 rather than in February 2016, as previously scheduled.
The company did not disclose the specific vessel to be delayed, but shipyard data shows Gulfmark has a 4,700dwt platform supply ship on order at the Simek yard, which is located at Flekkefjord. The contract was inked in April 2014.
Gulfmark has already paid 20% of the contract price (around US$8.25m) and says it has rescheduled the remaining payments.
Rather than making the planned balloon payment of US$33m on delivery, Gulfmark says it will pay approximately US$2m this quarter, US$5m in the first quarter of 2016, US$4m in the second quarter and US$22m in the first quarter of 2017 upon the vessel's delivery.
Gulfmark Offshore Delays Delivery of PSV from Simek Shipyard
2015-12-18
2730人
Source:Splash
Most ViewsHOT
- Densay expands tanker newbuild drive in China
- Holiday Notice
- Nanjing Tanker extends fleet renewal with Dalian brace
- Nanjing Tanker inks $51m ethylene carrier order
- Chinese Shipbuilder DSIC Delivers Its First LNG Carrier, Sea Spirit
- Jiangsu Ocean Shipping firms up boxship newbuild brace
- Itochu returns to New Dayang for fresh ultramax pair
- Vogemann linked to six kamsarmaxes at Hengli Heavy
- Hengli Heavy seals deal for up to four VLCCs
- Zhongxin Funeng seals boxship newbuild quartet