NYSE-listed Gulfmark Offshore has delayed the delivery of a newbuilding under construction at Norway's Simek shipyard by 11 months.
The vessel, which is being constructed for use in the North Sea, will now hit the water in January 2017 rather than in February 2016, as previously scheduled.
The company did not disclose the specific vessel to be delayed, but shipyard data shows Gulfmark has a 4,700dwt platform supply ship on order at the Simek yard, which is located at Flekkefjord. The contract was inked in April 2014.
Gulfmark has already paid 20% of the contract price (around US$8.25m) and says it has rescheduled the remaining payments.
Rather than making the planned balloon payment of US$33m on delivery, Gulfmark says it will pay approximately US$2m this quarter, US$5m in the first quarter of 2016, US$4m in the second quarter and US$22m in the first quarter of 2017 upon the vessel's delivery.
Gulfmark Offshore Delays Delivery of PSV from Simek Shipyard
2015-12-18
2909人
Source:Splash
Most ViewsHOT
- Eastern Pacific adds fresh suezmax pair in China push
- Peter Döhle extends boxship run with Chengxi contract
- COSCO targets dozen LNG dual-fuel boxships in $2bn move
- Zhonggu Logistics backs Wuhan Qingshan restart with 10-ship order
- Erasmus taps Huangpu Wenchong for boxship newbuilds
- Ciner adds six ultramaxes in fresh $204m China order
- Ningbo Ocean Shipping lines up fresh feeder boxship order
- China Merchants Energy stacks orderbook with 10-ship VLCC series
- Schoeller books more MPP tonnage in China
- Seacon lifts four MPP newbuilds in $44m fleet play