NYSE-listed Gulfmark Offshore has delayed the delivery of a newbuilding under construction at Norway's Simek shipyard by 11 months.
The vessel, which is being constructed for use in the North Sea, will now hit the water in January 2017 rather than in February 2016, as previously scheduled.
The company did not disclose the specific vessel to be delayed, but shipyard data shows Gulfmark has a 4,700dwt platform supply ship on order at the Simek yard, which is located at Flekkefjord. The contract was inked in April 2014.
Gulfmark has already paid 20% of the contract price (around US$8.25m) and says it has rescheduled the remaining payments.
Rather than making the planned balloon payment of US$33m on delivery, Gulfmark says it will pay approximately US$2m this quarter, US$5m in the first quarter of 2016, US$4m in the second quarter and US$22m in the first quarter of 2017 upon the vessel's delivery.
Gulfmark Offshore Delays Delivery of PSV from Simek Shipyard
2015-12-18
2658人
Source:Splash
Most ViewsHOT
- Chartworld eyes New Dayang boxships
- Fujian Highton readies $65m for bulker fleet expansion
- Jinhui agrees third supramax sale
- TS Lines locks in up to 10 newbuilds at Huangpu Wenchong
- BHP signs charters with COSCO for ammonia-powered newcastlemax newbuilds
- Jinhui frees up capital with double leaseback deal
- MSC ramps up megamax expansion with $1.2bn shipbuilding deal in China
- Winning Shipping acquires a newcastlemax
- Caravel Group sheds Kamsarmax fleet
- Latsco in for Huangpu Wenchong boxship brace