NYSE-listed Gulfmark Offshore has delayed the delivery of a newbuilding under construction at Norway's Simek shipyard by 11 months.
The vessel, which is being constructed for use in the North Sea, will now hit the water in January 2017 rather than in February 2016, as previously scheduled.
The company did not disclose the specific vessel to be delayed, but shipyard data shows Gulfmark has a 4,700dwt platform supply ship on order at the Simek yard, which is located at Flekkefjord. The contract was inked in April 2014.
Gulfmark has already paid 20% of the contract price (around US$8.25m) and says it has rescheduled the remaining payments.
Rather than making the planned balloon payment of US$33m on delivery, Gulfmark says it will pay approximately US$2m this quarter, US$5m in the first quarter of 2016, US$4m in the second quarter and US$22m in the first quarter of 2017 upon the vessel's delivery.
Gulfmark Offshore Delays Delivery of PSV from Simek Shipyard
2015-12-18
2713人
Source:Splash
Most ViewsHOT
- Hengli Heavy seals deal for up to four VLCCs
- Zhongxin Funeng seals boxship newbuild quartet
- Minerva Marine firms up feeder options at Yangzijiang
- Allseas orders heavy transport vessel in China
- Lepta Shipping books more LPG newbuilds in China
- Jinjiang Shipping in for up to four feeder newbuilds
- Ciner charts return to boxships with China newbuilds
- Ningbo Ocean Shipping looks to Singapore for global fleet expansion
- Asiatic Lloyd orders two boxships in Dalian
- Young Chinese carrier moves into ownership with boxship newbuilds