NYSE-listed Gulfmark Offshore has delayed the delivery of a newbuilding under construction at Norway's Simek shipyard by 11 months.
The vessel, which is being constructed for use in the North Sea, will now hit the water in January 2017 rather than in February 2016, as previously scheduled.
The company did not disclose the specific vessel to be delayed, but shipyard data shows Gulfmark has a 4,700dwt platform supply ship on order at the Simek yard, which is located at Flekkefjord. The contract was inked in April 2014.
Gulfmark has already paid 20% of the contract price (around US$8.25m) and says it has rescheduled the remaining payments.
Rather than making the planned balloon payment of US$33m on delivery, Gulfmark says it will pay approximately US$2m this quarter, US$5m in the first quarter of 2016, US$4m in the second quarter and US$22m in the first quarter of 2017 upon the vessel's delivery.
Gulfmark Offshore Delays Delivery of PSV from Simek Shipyard
2015-12-18
2758人
Source:Splash
Most ViewsHOT
- Greek owners Economou and Laskaridis extend VLCC order boom at Hengli
- Thenamaris returns to tanker newbuilds with suezmax brace in China
- Fujian Guohang drops two bulker orders at Jiangsu Haitong
- Star Bulk tied to fresh kamsarmax orders at Hengli
- Costamare lifts Chinese newbuild series to six boxships
- Latsco firms up boxship brace at Huangpu Wenchong
- Ebe breaks new ground with Chinese newcastlemax order
- COSCO unveils $1.75bn shipbuilding spree for 29 new vessels
- Capital Maritime adds capesize brace to expanding Chinese orderbook
- New Pure Car and Truck Carrier Delivered to Grimaldi Group by Chinese Shipbuilder