NYSE-listed Gulfmark Offshore has delayed the delivery of a newbuilding under construction at Norway's Simek shipyard by 11 months.
The vessel, which is being constructed for use in the North Sea, will now hit the water in January 2017 rather than in February 2016, as previously scheduled.
The company did not disclose the specific vessel to be delayed, but shipyard data shows Gulfmark has a 4,700dwt platform supply ship on order at the Simek yard, which is located at Flekkefjord. The contract was inked in April 2014.
Gulfmark has already paid 20% of the contract price (around US$8.25m) and says it has rescheduled the remaining payments.
Rather than making the planned balloon payment of US$33m on delivery, Gulfmark says it will pay approximately US$2m this quarter, US$5m in the first quarter of 2016, US$4m in the second quarter and US$22m in the first quarter of 2017 upon the vessel's delivery.
Gulfmark Offshore Delays Delivery of PSV from Simek Shipyard
2015-12-18
3146人
Source:Splash
Most ViewsHOT
- Winning locks in decade-long yard pact with Qingdao Beihai
- Veritas books fresh ultramax pair at COSCO yard
- Ningbo Marine maps out five-ship bulker expansion
- Medcare linked to five-ship MR1 order in China
- Yangzijiang Maritime moves into stainless chemical tankers
- Jiahua Energy enters shipping with CIMC SOE newbuild
- RCL heads back to Huangpu Wenchong for boxship quartet
- ASL scales up with Huangpu Wenchong boxship order
- Evalend reloads at Yangzijiang with $220m LR1 quartet
- Hudong-Zhonghua details expansion plans